Thursday, May 8, 2014

Rough-in of Electrical, HVAC and Plumbing 4/27/2014

House was wrapped in waterproofing membrane! 




Some of the back porch was built around the tree.  I think this means we can call our house a "tree house," right?

One of the AC units, in the crawlspace.

HVAC drop-ins in the living room/kitchen.

Electrical rough-in work started, not much to see, but exciting nonetheless!

Jonathan, tight rope walking out onto the back porch, off the master bedroom.

Plumbing in the master bedroom.

Master bathroom plumbing rough-in.  That is where the sinks will reside.

Monday, April 14, 2014

Roof Decking - 4/13/2014

Roof decking was almost completed on Sunday, waterproofing wrap was to be placed Sunday afternoon and Monday. 




Back porch still hasn't been built out all the way.

Ronnie, finishing up the last section of the roof decking!

Back of the house...

View into living area/kitchen, as you ascend the stairs.  There will eventually be a low wall there, but for now, you can see into the living room.

Living room and kitchen.

Little box opening is where the flood vents go.  This allows water to flow through the bottom level of the house in the event of a big flood or the nasty "H" word (HURRICANE)!